S.No Client Name Projects Name Length in Km

1

M/s JKM Infra Projects Limited.

“Widening and Strengthening of existing Single Lane/Intermediate Lane to Two Lane Carriageway with paved shoulders including geometric improvement from Km.68+260 to Km.118+370 of NH-59 in the State of Odisha” NH-59

50.11

2

M/s KNR Mzaffarpur-Barauni tollway Pvt ltd

Two laning of Muzaffarpur-Barauni section of , NH-28 From km 519 to km 627 in the state of Bihar on DBFOT(Toll)- EPC contract NH-28

108

3

M/s KNR Constructions Ltd

Rehabilitation and upgradation of existing NH-565 from Km 425/400 to Km 509/400 (Penchelakona to Yerpedu section) to two lane with paved shoulder in the State of Andhra Pradesh under NHDP –IV through Engineering, Procurement & Construction (EPC) Basis NH-565

84

4

M/s PSK Infrastructure and Projects Pvt Ltd

Detailed Design Consultancy Services” for “Upgrading Malliyakarai – Rasipuram – Thiruchengode – Erode Road (SH 79) km 0/000 to km 30/600 and km 51/400 to km 71/300 in the State of Tamilnadu SH 79

50.5

5

M/s SRK Constructions And Projects Private Limited

Widening and improvement from Mydukur to Dornala T Jn from Km.589/0 to 641/0 of NH 67 in the State of Andhra Pradesh through Engineering, Procurement and Constructions (EPC) Basis NH-67 Pkg-1

52

6

M/s SRK Constructions And Projects Private Limited

Rehabilitation and Upgradation of existing NH-67 from Km.641/000 to Km.695/000 (Dornala T Jn to Atmakur Section) to two lane with paved shoulder in the state of Andhra Pradesh under NHDP - IV through EPC Basis Contract. NH-67 Pkg-2

54

7

M/s. Sri Balaji Tollways (Madurai) Pvt. Ltd

Widening the Madurai Ring Road from Double Lane to Four Lane from km 0/0 to km 27/2 on BOT (Toll)”. R&B, Madurai ORR

27.2

8

M/s. Sri Balaji Tollways (Madurai) Pvt. Ltd

Four Laning of Bijapur – Hungund section of NH-13 (New -50) from Km.225.800 to Km.323.015 in the State of Karnataka under NHDP Phase III on Design, Build, Finance, Operate and Transfer (DBFOT) Toll Basis (Packege No: NHDPIII/BOT/KNT/05) NH-50(Old NH13) PUP/CUM-1 No & VUP -1 No

2

9

M/s IJM Infrastructure

Widening & Up-gradation of Dewas Bypass road from Km 0+000 at Ujjain Dewas Junction and Ends at Km 19+800 starts at Indore Junction to Four / Six laning of in the State of Madhya Pradesh on DBFOT basis Dewas Bypass

19.8

10

M/s Raj Promoters and Civil Engineers Pvt Ltd

Balance work of four laning from Km.153.000 to Km.175.000 of Nagpur - Hyderabad Section of NH-7 in the State of Maharashtra - on item rate mode NH-7 (Nagpur-Hyderabad)

0

11

M/s KMV Projects Limited

Rehabilitation and Upgradation to Two Lane with Paved Shoulders from Km 0/000 to km 72/600 of NH- 365 from Nakrekal to Tanamcherla Road in the State of Telangana NH-365 (Nakrekal)

72.6

12

M/s HES Infra Private Limited

Widening to 2/4 Lane with Paved shoulders from Km 182.120 to Km 227.600 of NH 167 on Haggari to Jadcherla road on Engineering, Procurement & Construction  (EPC) mode under NH (O) in the state of Telangana" NH 167

45.48

13

SE , Coimbatore

Preparation of Detailed Project Report for the work of Construction of Elevated Bridge for a length of 5.40Km from Kalingarayan Illam to Thindalmedu (Km.2/0 to Km.7/4 of Erode –Perundurai – Kangeyam road) Erode

5.04

14

Divisional Engineer (H), Projects, Salem

Preparation of Detailed Project Report in Bus Stand Arm for the main work of "Construction of Grade Separator at Km.1/8 of Erode - Perundurai - Kankeyam road near Government Hosipital" Erode Bus Stand Arm

1

15

M/s Adilabad Expressway Pvt Ltd

Desing, Construction, Development, Finance, Operation and Maintenance of Km.175.000 (Mah/Telangana Border) to Km.230.000 (Islamnagar) on NH-44 in the state of Telangana NH-44

55

16

M/s Sri Avantika Contractors (I) Limited

Construction of 2 lane with paved shoulder from Km.168.000 to Km.168.000 to Km.183.783 (Yesmong to Unger) on Mokkochung to Tuli Section of NH-61, Nagaland State NH-61 (Nagaland)

15.783

17

M/s KNR Constructions Ltd

Four laning of NH-161 from Ramsanpalle village (Design Km 39.980/Existing Km 44.757) to Mangloor village (Design Km 86.788/Existing Km 91.350) (Design Length -46.808 Km) in the State of Telangana under Bharatmala Pariyojana on Hybrid Annuity Mode NH-161 (Ramsanpalle-Mangloor)

46.808

18

M/s KNR Constructions Ltd

Six laning of NH-140 from Chittor (Design Km 0.000/Existing Km 158.000 of NH-4) to Mallavaram (Design Km 61.128/Existing Km 41.800 of NH-140) (Design Length = 61.128 Km) in the State of Andhra Pradesh under Bharatmala Pariyojana on Hybrid Annuity Mode NH-140 (Chittor - Mallavaram)

61.128

19

M/s Patel KNR JV

Design, Construction, Development, Operation, Finance and Maintenance of Islam Nagar (Km.230.00) t oKadtal (Km.278.00) of Nagpur - Hyderabad Section on NH-7 in the State of Andhra Pradesh, Under North - South Corridar (NHDP Phase-II0 on BOT (Annuity) Basis NH-7 (Nagpur - Hyderabad)

48

20

M/s VDB Projects Pvt Ltd & Sri Venkateswara Constructions

Widening and Strengthening of existing 2-lane to 2-lane with paved shoulders from Km 159/0 to 165/4 and Km 186/0 to 215/0 of NH-163 in the State of Telangana on EPC mode NH-163

35.4

21

M/s EKK Infrastructure Limited

Four - Laning Of Thalassery - Mahe Bypass Section Of NH-17 From Km 170.600 (design Chainage 170.600) To Km 188.000 (design Chainage Km 189.200) Under NHDP Phase-III On EPC Mode in the State Of Kerala Thalassery-Mahe Bypass (NH-17)

17.4

22

M/s PLR Projects Private Limited

Four Laning of Imphal – Moreh Section of NH 39 from Km 330+000 to 350+000 in the State of Manipur (Package I) Imphal - Moreh NH-39

20

23

M/s SPK & CO

Six Lanning of Karaipettai to Walajapet Section of NH-4 (New NH-48) from Km.71+015 (Existing Km 71/000) to Km 107+091 (Existing Km 107/068) on EPC Mode in the state of Tamil Nadu under NHDP Phase-V Karaipettai to Walajapet

36

24

D.P Jain & Co. Infrastructure Pvt Ltd

Four Laning of Madathukulam - Pollachi section of NH-209 (New NH-83) from Design Km. 74.380 to Km. 116.950 (Total Length – 50.078 km) under Bharatmala Pariyojana Phase-I under the category of Residual Works of NHDP on HAM in the State of Tamil Nadu Madathukulam - Pollachi

42.57

25

M/s JSR Infra Ltd

Construction of Four Lane divided Highway from Melur (Design Km.0.000/ Existing Km.99.920 of NH-38) to Karaikudi (Design Km.45.855/ Existing Km.12.900 of NH-383 Ext.)Design Length Km.45.855 Km) in the State of Tamil Nadu under Bharatmala Pariyojana on EPC Melur to Karaikudi

45.85

26

M/s KNR Constructions Limited

Four Laning of Trichiraopalli (Km.0.000) to Kallagam (Km.38.700) Section of NH-227 on Hybrid Annuity Mode in the State of Tamil Nadu under NHDP Phase IV Trichiraopalli- Kallagam

38.7

27

M/s Anusha Projects Private Limited

Widening and Strengthening / Reconstrution of existing pavement to Four lne with paved shoulders from Km.266.348 to Km.283.000 of Mahabubnagar-Jadcherla section of NH-167 on EPC mode in the state of Telangana Mahabubnagar - Jadcherla

16.65

28

M/s Brij Gopal Construction Company Pvt Ltd

4-Lanning of Jind - Gohana (Pkg-I) section (Greenfield Alignment) from Km.0.000 to Km.40.601( Length 40.601 Km) of NH-352A in the State of Haryana under NH(O) on Hybrid Annuity Mode Jind-Gohana

40.601

29

M/s JMC Constructions Pvt Ltd

Rehabilitation and Upgradation of Chittoor - Kurnool Road NH-18 (New NH-40) from 2 lane to 4 lane from Km.4/14 to Km.18/34 (Excluding 2.94 km ROB Portion) from Murkumbattu Junction to Rangampet Cross in the state of Andhra Pradesh under Corridor approach Through EPC mode under NH(O) Chittoor-Kurnool Road

14.2

30

M/s P Venkateswara Rao

Widening of Bottelneck at Punjagutta Grave for rectification of Black spot area under T &T GHMC Punjagutta

0.2

31

M/s P Venkateswara Rao

Improvement of Radial Road No.30 i.e. from Hyderabad Central University Depot to Vattinagulapply Village on Outer Ring Road in Ranga Reddy District – (Part of the work with Drawn under Clause 60 @ of APDSS) Goppanapalli

1.3

32

M/s Anusha Projects (P) Ltd

Widening of existing single/ intermediate lan road to 2 lane road from Km.83.00 to Km.101.00 on NH-61 in the state of Nagaland Nagaland (NH-61)

18

33

M/s D.P Jain & Co. Infrastructure Pvt Ltd

4-Laning of Nagpur - Umred section from Km.7+300 to Km.48+400 (Package -I) of NH-353D in the state of Maharashtra on EPC mode - Detailed Design Consultancy services for Major Bridges (4 Nos) and VUP (1 No) Nagpur-Umred

1

34

M/s KNR Constructions Ltd

Four laning of Oddanchatram - Madathukulam section of NH-209 (New NH 83) (Design Ch Km.29.000 to Km 74.380) under Bharatmala Pariyojna Phase-I under the category of Residual works of NHDP on HAM in the state of Tamil Nadu Oddanchatram - Madathukulam (NH-209)

45.38

35

M/s HG Infra Engineering Ltd

Four laning of NH-363 from Mancherial Design Km 0.000 Existing Km 251.900 to Repallewada Design Km 42.000 Existing Km 288.510 Design Length 42.000 Km in the State of Telangana under NHDP Phase-IV under Bharatmala Pariyojana on Hybrid Annuity Mode Mancherial - Rapallewada (NH-363)

42

36

M/s J Kumar Infraprojects Ltd

Construction of Dwarka Expressway between design chainage 5+300 and 9+500 (Package 2) in State of Delhi Dwaraka Expressway

4.2

37

M/s P Venkateswara Rao

Steel Bridge To Provide access Road Into Panjagutta Graveyard Opp: Chutneys And For Development Of Exit road For Graveyard From Road No.1 Side Panjagutta

0.1

38

HG Infra Engineering Ltd

Construction of Proposed Rewari Bypass (designed length 14.4 km) as a Feeder Route in the state of Haryana on Hybrid Annuity Mode Rewari Bypass

14.4

39

M/s CEIGALL

Construction of Six-Lane access controlled highway (NH-152D) starting from Ismailabad on NH-152 to Junction with Karnal- Pehowa road (SH-9) near Dhand [Ch. 0+000 to Ch. 23+000 length 23 km] section of NH-152D Greenfield Alignment on EPC Mode under BharatmalaPariyojana in the State of Haryana Ismailabad - Karnal - Pehowa Road

23

40

M/s R&B, Warangal

Detailled Design Engineering Consultancy Services for Exit Road Flyover of 6-Lane Ring Road at Yadadri in Yadadri - Bhuvangiri District Yadadri Exit Road Flyover

06

41

M/s Sadbhav Engineering Ltd

Four Laning of Bijapur - Hungund Section of NH-13 from Km.102.000 to Km.202.000 in the State of Karnataka under NHDP Phase III on Design, Build, Finance, Operate and Transfer ("DBFOT") Toll Basis (Package No NHDP-III/BOt/KNT/05) - Detailed Engineering Surveys & Design of Service Road / Structure at Hittanhanalli Villaage Bijapur - Hundund

1.1

42

M/s Anusha Projects (P) Ltd

Rehabilitation and Upgradation to 2-lane with paved shoulders of Rulcham - Dulte section (Economic Corridor) of NH-6 from existing chainage Km.50+360 (Rulcham) to Km.69+015 (Dulte) (Design Chainage Km.45+040 to Km.62+200) (Pack -IV) in the state of Mizoram under Bharatmala Pariyojana on EPC mode Rulcham - Dulte Section (Mizoram)

18.6

43

M/s R&B, Warangal

Forming 6 Lane Ring Road around Yadadri Temple along with new Ghat road landing towards N-E 1st Flyover Near 1st Ghat Road Yadadri Bhongir - 1st Flyover

0.4

44

M/s KCP Engineers Pvt Ltd

Construction of flyover at Km.362/790- 364/555 of (Nagapattinam - Gudalur - Mysore Road) Periyanaickenpalyam Junction - Coimbatore - Outskirt in the state of Tamilnadu on EPC Flyover Bridge at Periyanaickenpalayam

1.76

46

M/s Megha Engineering & Infrastructures Ltd

Six Laning of Chengala to Neeleshwaram section of NH-17 (New NH-66) from Ch. 56+200 (existing Km.57+200) to Ch.93+468 (existing Km 95+650) Total length 37.268 km in the State of Kerala on Hybrid Annuity Mode under Bharatmala Pariyojna in the Category of residual works under NHDP Chengala to Neeleshwaram

38.45

47

M/s Megha Engineering & Infrastructures Ltd

Six Laning of Neeleshwaram to Thaliparambha section of NH-17 (New Nh-66) from Ch.94+540 (existing Km.96+450) to Ch.134+650 (existing Km.137+900) in the State of Kerala on Hybrid annuity mode under Bharatmala Pariyojna in the Category of residual works under NHDP Neeleshwaram to Thaliparambha

43.36

48

M/s Megha Engineering & Infrastructures Ltd

Six Laning of NH-71 from Renigunta (Start at junction of NH-71, NH-18A,NH-205 MDR of Renigunta) (Design Km.0.000/ /Existing Km.124.600 of NH-71) to Naidupeta (End on NH-16) Design Km.57.046/ Existing Km.183+400 of NH-71) (Design Length = 57.046 Km) on Hybrid Annuity mode in the State of Andhra Pradesh under Bharatmala Pariyojana Renigunta - Naidupeta

57.046

49

M/s RPP- Dhanya (JV)

Upgrading Kanchipuram - Arakkonam - Thiruthani Road section of SH-58 from km 66.940 to km 86.345, km103.260 to km 108.719 and construction of Arakkonam bypass from km 86.345 to km 103.260 (16.915km) to two (2) lane with paved shoulders for a total length of 41.779 km and maintenance of entire project stretch for 7 years in the State of Tamil Nadu on Engineering, Procurement and Construction (EPC) Mode Annuity mode Kanchipuram-Arakkonam- Thiruthani

41.779

50

M/s RPP- Renaatus (JV)

Upgrading of Malliyakarai – Rasipuram – Tiruchengode - Erode Road (SH 79) from km 83/350 to km 91/100 to Four lane with paved shoulders and Construction of Two Lane Elevated Corridor from Ch. 91/100 to Km 94/170 including Service road on either side and providing ramp to Sankagiri Pallipalayam Road from km 15/367 to km 15/700 (Design Chainage 0/000 to 0/333) and maintenance of entire project stretch of 11.153 km for a period of 7 years Malliyakarai – Rasipuram – Tiruchengode - Erode Road

11.1

51

M/s Krishi Infratech

Construction of Bridge across Tunga river at Km.207.80 of NH 206 Tumkur - Honnavara section in the state of Karnataka on Engineering, Procurement & Construction (EPC) Basis Bridge acroos Tunga River

1

52

M/s Krishi Infratech

Construction of Two lane steel composite ROB at Km.525.00 of NH-13 Chitradurga - Shimoga section in lieu of LC-46 (Railway Chainages Km.60.830) in the state of Karnataka on EPC mode ROB - Chitradurga - Shimoga

1

53

M/s Krishi Infratech

Construction of 4 lane ROB at Km.4/0 - 4/1 between Gudivada - Nujella Station on Gudivada - Machilipatnam section ata N.H Km.10+906 on Pamarru and Alapadu Bypass road of NH-165 in Krishna District i the state of Andhra Pradesh Gudivada - Machilipatnam

0

54

M/s KUDA Warangal

1. Widening of existing BT road to double lane (two lane) in Jawahar colony junction at Gopalpur village, Hasanparthy (M), Warangal (U) District - Package I - 7.23 Km.
2.Formation of BT road from MAA Township to Anantha Sagar Village to meet Karimnagar Warangal road, Hasanparthy (M) Warangal (U) District - Package -II - 6.52 Km
Gopalpur Village & Anantha Sagar Village

13.75

 

 

  Total

1485.345